Park Construction Update

Phase I Project Update:

           March 2018

  • Building exterior finishes
  • Curb and gutter installation
  • Dog Park chain link fence installation
  • Rough site grading

           October 2017

  • Roadway subgrade stabilization has begun
  • Dry detention area excavation ongoing
  • Lake excavation is complete
  • Site balancing/earthwork is ongoing
  • Gazebo structural member installation complete
  • Sidewalk installation is ongoing

           August 18, 2017

  • Construction of the underground stormwater system is complete
  • Sanitary sewer for the building has been installed and will soon be connected by the plumber
  • Lake excavation is ongoing
  • Site balancing/earthwork is ongoing
  • Gazebo installation has begun
  • The building is dried-in (rain will no longer affect the building)

    July 3, 2017
  • Excavation of the lake
  • Underground stormwater utility installation
  • Construction of sidewalks and picnic areas
  • Installation of the masonry walls for the restroom storage building
  • Electrical work