About Island Way South

ProposedAlignment.pngIsland Way South will provide a southern extension of the existing N. Island Way roadway, which currently connects to W. Indiantown Road from the north just west of Central Boulevard. Island Way South will provide an alternate route that will alleviate some traffic from Indiantown Road and Central Boulevard.

Project improvements include traffic safety measures and pedestrian facilities to maintain and enhance the neighborhoods’ livability. A roundabout is planned just south of Indiantown Road.

Island Way South is identified in the Town's strategic plan as a priority by the Town Council and is funded in the 5-year Community Investment Program (CIP). It's purpose is to mitigate traffic and to provide access to parcels identified for future development. In 2009, an alignment study was conducted to show impacts on the surrounding neighborhoods, which provided insight into potential design options.

View a conceptual drawing of the proposed roadway alignment (larger view of what is shown to the right).

Island Way South Impacts & Benefits

The Town has assembled a working group to provide input, assist with outreach and communication, and discuss impacts and benefits of the proposed plan. The group is expected to meet again in Fall, 2016.  Below are some of the areas of benefit and impact discussed by the working group to-date. 

  • Improvement to the overall performance of the local roadway network.
  • Connection from Jupiter Park Drive to Indiantown Road. 
    • Redirect some traffic from Indiantown Road between Island Way and Central Blvd. It is expected that the new roadway will divert approximately 5,000 trips daily between Island Way and Central Boulevard.
    • Improve the performance of the roadway section and the Central Blvd. intersection. 
  • Some impacts on the adjacent neighborhoods expected.
    • Higher volumes of traffic near Bakers Park and Kennedy Estates
    • Town Council direction to evaluate third connection to I95 (in addition to ITR and Donald Ross Rd.) may mitigate some traffic impacts in northwest Jupiter.
  • Possible opportunities:
    • Buffering along residential immediately adjacent to Island Way.
    • Enhanced landscaping.  
    • Providing an entry feature for the neighborhood.
    • Pedestrian/bicycle opportunities.
    • Parks or recreation opportunities, boat launch/fishing along the canal.

Anticipated Project Process and Timeline

 Nov/Dec 2016    Acquisition of PBC right-of-way (PBC BCC approval)
 Dec 2016    Hawkeye Property Development Agreement or Eminent Domain
 Feb 2017    Eminent Domain process and Project resolution (Town Council approval)
 Dec 2017    Design Approval (Town Council approval)
 March 2018    Construction Bid Award (Town Council approval)
 June 2018    Construction Begins

Stay Up-to-Date

Based on the schedule for this project, various items will be coming before the Town Council for approval.

  • On Tuesday, August 16, the Town Council will consider an item to approve a work order with Calvin Giordano and Associates.  Approval of this item would mean the engineering firm can begin working on the technical design and specifications of the roadway and amenities, including landscaping, improved pedestrian access, and recreational features.

    This agenda item and supporting documentation will be available online at the afternoon of August 9.

If you would like to subscribe to a mailing list to receive Town Council agendas, click here.  Also, all Town Council regular meetings are broadcast live on the web and available on-demand at